Welcome to the second edition of The Grounds Project News.

With the winter chill starting to set in, site works at The Grounds is starting to heat up.

Demolition and site clearance is on track to be completed in the next few weeks. Early work for service and infrastructure upgrades have commenced.

The drainage service and infrastructure upgrades are staged. On site works will be completed at the end of June. Following this, works will commence on Irvine Road and will take approximately
6 weeks.

The upgrades will significantly increase drain capacity and reduce the probability of localised flooding to occur. This will benefit the wider Ivanhoe community.

We look forward to keeping you posted with the latest construction news throughout 2019. The Grounds team is available via email at info@thegroundsivanhoeeast.com.au